VIEUX FORT, St Lucia — Opposition Leader Allen Chastanet called the St Jude Hospital handover “the greatest con in our nation’s history,” accusing the Labour administration of misleading the public as patients in southern St Lucia wait for the rebuilt facility to open fully. Health Minister Moses Jn Baptiste said Nov. 16 that he expects the remaining services to move in 2027, without giving a firm date.

Writing on Facebook on the first anniversary of the handover, Chastanet called on Prime Minister Philip J. Pierre to give residents a firm opening date and disclose how much the government had spent on the reconstruction and what work remained.
Patients still receive care at two sites. Dialysis and physiotherapy are operating at Augier, while the hospital’s patient information directs patients to the emergency department at George Odlum Stadium. Hospital operations moved to the stadium after a fire damaged the original facility in September 2009.
In an August 2023 interview, Lydia Atkins, then CEO of St Jude Hospital, said staff had spent 14 years caring for patients in a stadium never designed to serve as a hospital. She said employees who had worked under pressure for years welcomed the prospect of returning to Augier.

In September 2024, the Office of the Prime Minister acknowledged the strain on hospital staff as the government prepared to award contracts for the final phase of construction.
What delayed the move after the St Jude Hospital handover
At the Nov. 16, 2025, handover, Pierre described the rebuilt hospital as “a promise fulfilled.” The government said construction was complete and the handover would allow the Ministry of Health to begin commissioning the facility, which involves preparing equipment, systems and procedures for patient care.
Services moved in phases. In April, the Ministry of Health said physiotherapy had fully relocated, administrative and finance staff were working at Augier, and laundry operations had begun there. The kitchen and dialysis unit were still being prepared.
The hospital said dialysis moved to Augier on July 28 and that treatment continued without interruption during the transfer. By the November briefing, Jn Baptiste said kitchen operations had also moved and that the services already operating at Augier were benefiting hundreds of patients.
In April, the ministry had said it expected services to be fully restored within a few months. At the November briefing, Jn Baptiste said specialists had identified additional work and that safety checks and system verification had taken longer than anticipated.
He said teams still had to verify electrical and water systems, medical gas supplies, ventilation and systems used in services involving radiation. Staff also needed training on new equipment, layouts and safety procedures. Technical advisers, consultants, trainers and specialized engineers were helping prepare the remaining departments for the move, he said.
Chastanet presses for a date and a spending breakdown
Chastanet said the United Workers Party had warned against returning to the original hospital site. He cited an FDL report that he said raised concerns about the building layout, fire safety and infection control. He argued that completing a separate, purpose-built hospital already under construction would have cost less and brought patients into a fully functioning facility sooner.

In his post, Chastanet pointed to families seeking emergency care and nurses who have worked at the stadium for years as reasons the government should give the public a firm date. He thanked the doctors, nurses and other staff who had kept the hospital operating and asked the government to explain the decisions behind the delay.
Chastanet also questioned the projected cost of completing St Jude Hospital in 2024, citing figures in the government’s 2024–25 budget estimates. The Office of the Prime Minister said in 2024 that the government had secured EC$201 million in loan financing from the Saudi Fund for Development for the reconstruction.
Jn Baptiste accused the opposition of applying a double standard. He said the former UWP administration took nearly four years to fully move services into Owen King EU Hospital after receiving the facility in 2016. The move was completed during the COVID-19 pandemic, he said.
Jn Baptiste said teams would finish testing hospital systems and making adjustments before more departments move to Augier. The government expects to complete the transfer in 2027 and has yet to announce when the emergency department will leave the stadium.